Cost |
Donation |
Donor or dedication |
|
ROCK EXCAVATION/FINISHING (or AUD200 per hour) |
40,000 |
|
|
|
ENTRY COLUMN (Concrete Structural) |
10,000 |
|
|
|
ENTRY STONE WORK |
2,500 |
|
|
|
FLOORING, FORMWORK, POLISHING (Concrete Slab) (or AUD200 per M2) |
44,000 |
|
|
|
WHITE PEBBLES |
700 |
700 |
Eva Blair |
|
BLUE METAL |
2,500 |
|
|
|
PIPING WHITE |
2,900 |
|
|
|
STORMWATER DRAINAGE PIPE |
1,000 |
1,000 |
Yap Tia Koh (Malaysia) |
|
CAVE DOOR |
2,000 |
2,000 |
Chandra Kumarasinghe |
|
CAVE DOOR FRAME |
2,000 |
|
|
|
Overall Costs |
107,600 |
|
|
Main Building Renovation
|
|
Cost |
Donation |
Donor or dedication |
TOP DECK (20 M2) |
$12,000 |
|
|
|
LOWER DECK (20 M2) |
$8,000 |
|
|
|
UPSTAIRS: SHRINE ROOM (80 M2) |
$25,000 |
$25,000 |
O Ba My’Tin, Mr. & Mrs. Vo Van Tam |
|
DOWNSTAIRS: COMMUNITY ROOM (80 M2) |
$20,000 |
|
|
|
STAIRS |
$15,000 |
|
|
|
Overall Costs |
$80,000 |
|
|
Breakdown of major supplies per unit
|
Location/Supply |
Cost/ unit |
# units |
Total cost |
Donation |
Donor or dedication |
|
UPSTAIRS |
|
|
|
|
|
|
Insulation (m2) |
$8 |
140 |
$1,120 |
|
|
|
Ceiling Timber (m2) |
$18 |
80 |
$1,440 |
|
|
|
Floor Heating (m2) |
$40 |
80 |
$4,800 |
$488 |
Teresa NG, Sweden |
|
Ceiling (m2) |
$16 |
140 |
$2,240 |
|
|
|
Plasterboard (m2) |
$8 |
80 |
$640 |
|
|
|
Floor Insulation (m2) |
$12 |
80 |
$960 |
|
|
|
Skylight |
$1,300 |
1 |
$1,300 |
|
|
|
UP/DOWNSTAIRS |
|
|
|
|
|
|
Flooring (m2) |
$40 |
160 |
$6,400 |
|
|
|
Floor Sanding (m2) |
$25 |
160 |
$4,000 |
$100 |
Sunil |
|
Steel Beams |
|
|
$3,500 |
|
|
|
DOWNSTAIRS |
|
|
|
|
|
|
Heater |
$3,000 |
1 |
$3,000 |
|
|
|
Window |
$130 |
1 |
$130 |
$130 |
Nishka |
|
Front Doors |
$350 |
1 |
$350 |
$350 |
Anonymous |
|
DECKS/STAIRS |
|
|
|
|
|
|
Decking (m2) |
$40 |
40 |
$1,600 |
|
|
|
Nails |
|
|
$150 |
$150 |
Bhagyo |
|
Balustrades (m) |
$60 |
16 |
$960 |
$60 |
Ng Swee Leong |
|
Steel curves |
$2,400 |
2 |
$,4800 |
|
|
|
Steel posts |
$125 |
4 |
$500 |
$500 |
Jintra |
|
Steel posts |
$130 |
6 |
$780 |
|
|
|
Stair treads |
$14 |
82 |
$1,148 |
|
|
All costs are in Australian Dollars and are estimates only. All donations will be put in a central fund and used for building and development of Santi Forest Monastery. For further payment options, see Donations.
Donations for building are tax-deductible in Australia. Please supply your name, amount donated, email, and address if you need a receipt.